Public Procurement Rules 2004
Home
/
Business Law
/
Public Procurement Rules 2004
- Page 15
Show/Hide Answers
Public Procurement Rules 2004
When an extension of time for submission of bids is made it must abide?
by recording reasons
by recording reasons in equal opportunity manner
extension shall be done is manner to original advertisement
All of these
Author:
rikazzz
Comment
Public Procurement Rules 2004
The object of Procurement brings______ to the agency and the procurement process is efficient and economical.
Value for money
Time saving
Value for shareholder
None of these
Author:
rikazzz
Comment
Public Procurement Rules 2004
According to methods of advertisement it is mandatory the advertisement principally appears is:
At least one Urdu daily
At least one English daily
At least one English and one Urdu daily
None of these
Author:
rikazzz
Comment
Public Procurement Rules 2004
while engaging in pre-qualification a procuring agency must take into consideration
relevant experience and past performance capabilities with respect to personal equipment and plant
financial position
appropriate managerial capabilities
All of the above
Author:
rikazzz
Comment
Public Procurement Rules 2004
how a contract deems to be closed
issue of delivery certificate
with the submission of final billl
incase of defect liability
All of the above
Author:
rikazzz
Comment
Public Procurement Rules 2004
While opening competitive bidding which envelope is to opened first:
Financial proposal
Technical proposal
Economic proposal
All of these
Author:
rikazzz
Comment
Public Procurement Rules 2004
A procedure leading to the award of a contract whereby all the interested persons, firms, companies or organizations may bid for the contract and includes both national competitive bidding and international competitive bidding is termed as:
Competitive bidding
Compete orders
Contract
Charter of Massive procurement
Author:
rikazzz
Comment
Public Procurement Rules 2004
a supplier may be blacklisted
a supplier constantly fail to provide satisfactory performance
found indulging in corrupt practices
found indulging in fradulent practices
All of the above
Author:
rikazzz
Comment
Public Procurement Rules 2004
alternative technical proposal are possible the bidding methods is adopted
single stage
two stage
Both (a) and (b)
None of the above
Author:
rikazzz
Comment
Public Procurement Rules 2004
for acquisition of spare parts or supplementary services for orignal manufacture, which method is applied
bid opened in presence of the bidders
alrernative method
Both (a) and (b)
None of the above
Author:
rikazzz
Comment
Page navigation
Previous Page
Previous
1
…
13
14
15
16
17
…
19
Next Page
Next
Go to Page
Light
Dark
GK
Pakistan Studies
Current Affairs
Islamic Studies
English